💡 For each process step in a Production Order, which you have configured under Processes, you can add one or more measurements linked to a specific time.
💡 You can also add multiple measurements to the same process step in the production order, each at a later time.
💡 Before you can use measurements, you must first create them. You can consult this 👉 guide for instructions.
⇢ Click on the line of a production order and then on the green icon Add measurements.
Process step: the process step in which the measurement was performed.
Date: the date on which the measurement was performed.
Time: the time at which the measurement was performed.
Measurement type: the type of measurement that was performed.
💡 If you have performed the same type of measurement multiple times, you can add each one by reopening this dialog window to add the next measurement.
💡 Each time you reopen the dialog window, you will no longer see the previous measurement results. These results can be consulted under Production - Measurements and in the production report.
Value: the value that was measured.
Remark: an optional field where you can provide additional information regarding the measurement result.